Tardebigge Top Lock Restored

A few days ago we completed the Tardebigge Lock Flight towards Birmingham through the now restored Top Lock 58, which had been closed for restoration since  17th February 2025.

The lock look beautiful, at the moment the cleanest canal lock we have ever been through, you can see all the new and old blue bricks on the left and the new blue bricks on the right.

Inside the restored Tardebigge Top Lock number 58

In the picture below, you can see the new bricks with one of the makers marks showing Ketley for Ketley Brick Company Ltd.

Ketley Blue Bricks

There is not much to see up top as the CRT team have left everything very tidy. We are very pleased to see the flight open as with other drought closures it has seriously curtailed our travels this year.

Note: Interestingly there are signs on the lock gates asking boater to leave the locks empty after use.

Tardebigge Lock Flight Open, but still restricted

The BBC has reported that the Tardebigge locks are now open for navigation (27th August) see report on BBC site

But as of the 27th of August the CRT has put a restriction on the flight starting at lock 23 and continuing to lock 58 due to the water shortage :-

Quote from CRT Website

Following the driest March–July period since 1921 across central England, water availability in the region remains significantly below average. To help conserve increasingly limited water resources, protect canal infrastructure and ecology, and prolong navigation elsewhere on the network, Tardebigge Lock Flight will be open under navigation restrictions from Wednesday 27th August. This date aligns with the expected completion of repairs to Tardebigge Top Lock.

Passage will be permitted between 8:30 am and 3:00 pm, with the last entry at 12:00 noon. Boaters are reminded that the final opportunity to turn around before ascending the flight is just after Lock 23.

We will continue to manage the limited water situation and will provide updates if conditions change. Despite the measures we’re taking, there may be extreme local circumstances that require us to take immediate action to temporarily close some stretches to navigation.

If sufficient rainfall occurs to allow safe navigation, restrictions will be lifted immediately. However, this is likely to require sustained and prolonged rainfall over several weeks, rather than a single heavy downpour.

Thank you for your continued support in reducing water use across the network and for reporting leaks or concerns via 0303 040 4040 or our Contact Us page

From CRT Website 30-08-2025

Tardebigge top lock update 25th June 2025

We took a drive up to see how the work on the Tardebigge top lock, on the Worcester and Birmingham Canal, was progressing this 200 year old lock flight must be a maintance headache for the CRT, but it is a major gateway to Birmingham and the rest of the network, if you don’t what to take the long route up the river Severn.

The Lock was closed on the 17th February 2025 and they hope to open it again by the end of August 2025, about 6 ½ months if all goes well.

Temporary Dam above the Tardebigge top lock
Behind the temporary dam above the Tardebigge top lock
Info sign at the Tardebigge top lock
The Paddle exposed inside the lock
Tardebigge top lock covered over while the work progresses
Downstream of the Tardebigge top lock

There seems to a team working away on getting this complete.

It has been recommended that if you want more detail on what is going on watch Martin Zero’s video on you tube

Also just published a Video from Court Above The Cut